Commonwealth Report Findings Land and water For policymakers Elected Officials Updates Weekly Method Search

Worcester County · Hubbardston, the front page ›

Hubbardston

Town · Worcester County · 4,371 residents (ACS 2020–24)

Data through FY2026; built November 9, 2026.

State House

State Senate

School districts

Regional planning agency

Montachusett Regional Planning Commission

Habitat, forest and water

Hubbardston: Land and Water ↗

This is what the state sends your town: aid, grants and earmarks, and how they compare with towns like it. What the money has to cover is on the other pages: the roads in flood zones, the land the state holds here, and the legislators whose posts shape the earmarks.

Hubbardston, in brief

Hubbardston is a town of 4,371 people on 41.1 square miles of Worcester County, 106 to the square mile, among the least densely settled fifth of the state. Median household income is $124,000, close to the median town’s $114,000. State aid covered 6.3% of its general-fund spending in FY2025; the median town’s share was 11.5%. On the Fairness Index it scores 59 for all state aid and 42 for discretionary money — above its share on all state aid, about its share on the money legislators and agencies choose to give. Its Land and Water Index is 74, 62nd of 351. The state owns 5% of its land, on which it paid $122,000 in lieu of taxes in FY2026, $86.03 an acre against $117 statewide. The forest now covers about 82% of the town, up from the 13% the surveyors drew in 1830. On the strong side: earmarks to its government came to $291,000 over ten state budgets, $66.58 per resident, 49th of 351; formula aid came to $16,583 per resident over ten years, 51st of 351; 53% of the town is protected open space of one owner or another.

Where it comes up short: measured against what it maintains, it received 33% of its proportional share of competitive grants.

The openings are specific: $823,000 of its Chapter 90 road money is apportioned and not yet drawn; the gap between what a statewide model of size, need and institutions predicts and what arrived is $836,000 over ten years. The risks are equally specific: it has lost 7.7% of its tree cover since 2001, 1.9 times the statewide rate, the largest year being 2018; emerald ash borer has been mapped in town by the aerial survey since 2019; a lake or river already listed for an invasive plant.

Written by rule from the figures on this page: each clause appears only when the town sits well away from the middle of the state on that measure, so a shorter story means a more ordinary record. Every figure is in the cards below with its source.

Hubbardston · 41.1 square miles

Fairness Index · all state aid

59 / 100

55th of 351 · stable high

Fifty is a fair share.

See the index ›

Fairness Index · discretionary money

42 / 100

220th of 351

Grants and earmarks only.

See the index ›

Land and Water Index

74 / 100

62nd of 351 · stable high

Fifty is the median town.

Full land page ›

At a glance

  1. Fairness IndexHubbardston scores 59 on the Fairness Index for all state aid and 42 for discretionary money. Fifty is a fair share.Read more ›
  2. State moneyHubbardston’s town government and school districts received $72.5 million in formula aid and $1.2 million in competitive grants over ten years.Read more ›
  3. EarmarksHubbardston received $291,000 in local earmarks in ten enacted state budgets on all three measures.Read more ›
  4. Aid and chargesIn FY2027 the state’s cherry sheet sends Hubbardston $756,000 and takes back $12,000 in assessments and charges, a net $743,000.Read more ›
  5. Money to othersState programs also awarded $143,000 to organizations in Hubbardston other than the town government, FY2016–FY2027.Read more ›
  6. Expected and actualHubbardston received $1.4 million in earmarks placed in the city or town and competitive grants over ten years, 63% of the $2.3 million its size, need and institutions predict.Read more ›
  7. What the town carriesMeasured against what it maintains, Hubbardston received 33% of its proportional share of competitive grant awards.Read more ›
  8. Roads and bridgesHubbardston has $823,000 of Chapter 90 road money from FY2017–FY2026 not yet reimbursed; it owns one bridge rated poor and no high- or significant-hazard dams.Read more ›
  9. Costs and the 2½% limitState aid covered 6.3% of Hubbardston’s general-fund spending in FY2025, down from 8.0% in FY2006.Read more ›
  10. State landHubbardston has 10,522 acres of mapped state conservation and recreation land and 1,802 acres of land coded as chapter land.Read more ›
  11. Habitat and waterHubbardston has 6,044 acres of mapped core habitat, 23% of its land area; 1,655 of those acres are outside any protected land.Read more ›
  12. SchoolsHubbardston’s required school contribution is 2.3% of median household income, 275th highest of 351.Read more ›
  13. School buildingsThe Massachusetts School Building Authority approved grants of up to $481,000 for schools serving Hubbardston, FY2017 to August 2026.Read more ›
  14. PeersHubbardston ranks 6th of 11 on earmark dollars placed in the city or town per resident among itself and its ten nearest peers.Read more ›

Fairness Index

Hubbardston scores 59 on the Fairness Index for all state aid and 42 for discretionary money. Fifty is a fair share.

All state aid

59 / 10055th of 351 (1 = most above its share)

Equal
59
Need
64
Burden
51
Effort
61

Rank under other weightings: 43rd to 66th.

Stable high: above 55 under every weighting

Hubbardston received more than its share of state aid on all four measures; its blended score of 59 stays between 56 and 61 under every weighting tested.

Discretionary money only

42 / 100220th of 351 (1 = most above its share)

Equal
44
Need
49
Burden
31
Effort
46

Rank under other weightings: 212th to 228th.

Weighting-dependent: the range crosses the 45–55 band

Hubbardston received less than its share of discretionary money on all four measures; its blended score of 42 stays between 40 and 46 under every weighting tested.

Each bar is one way of defining a fair share: Equal, the same per resident; Need, weighted toward poverty, low income and a thin tax base; Burden, by what each program pays for (road miles, bridges, pupils and so on); Effort, by what residents already pay in property tax relative to their income. The line marks 50. The score is the average of the four. Discretionary money is competitive grants and earmarks to the city or town government. How the index is built.

State money, FY2017–FY2026

Hubbardston’s town government and school districts received $72.5 million in formula aid and $1.2 million in competitive grants over ten years.

Formula aid

$72.5M

$16,583 per resident (51st of 351) · gross

Competitive grants

$1.2M

$264 per resident (224th of 351)

Earmark-account payments

$268,000

$61.39 per resident (52nd of 351)

Competitive grants to Hubbardston peaked in FY2020 at $427,000, 37% of the ten-year total.
Formula aid$72.5M total · peak $8.2M in FY2026
Competitive grants$1.2M total · peak $427,000 in FY2020
Earmark-account payments$268,000 total · peak $100,000 in FY2019
FY17FY18FY19FY20FY21FY22FY23FY24FY25FY26

Each class has its own scale. Bars show dollars paid in each fiscal year.

Formula aid is gross: Chapter 70 as DESE attributes it to the town, and cherry-sheet aid before the state deducts charges such as charter tuition and transit assessments, plus other formula programs as paid. Competitive grants and earmark-account payments are Comptroller payments to the town government and its school districts (stage: paid), the same payees as the Fairness Index. Enacted earmarks and earmark payments are different things: enacted earmarks are budget clauses, counted three ways above; earmark-account payments are Comptroller payments to the town government and its school districts from accounts classified as earmarks, which can include prior-year and statewide-program money. Either can be larger. Shared revenue, pass-through contracts, transfers to state entities and unclassified payments, $2.5M in all, are not shown. Rank 1 is the highest amount per resident among 351.

Earmarks

Hubbardston received $291,000 in local earmarks in ten enacted state budgets on all three measures.

To the city or town government

$291,000

$66.58 per resident (49th of 351)

Placed in the city or town

$291,000

$66.58 per resident (120th of 351)

Everything placed

$291,000

$66.58 per resident (127th of 351)

No earmarks in ten state budgets

No

35 municipalities had none

Local earmarks are counted three ways: money to Hubbardston’s government, its schools or municipal projects; money placed in Hubbardston, adding organizations; and everything placed, adding state facilities located here. Three ways to count a local earmark.

Placed in the city or town: five clauses in four of ten state budgets; the most recent in FY2025. All of it went to Hubbardston’s government, its schools or municipal projects.

Every local earmark in Hubbardston, FY2017–FY2026, largest first (five clauses; the town’s share where a clause names several towns)
YearAmountBudget text (excerpt)Stage
FY2019$100,000“the town of Hubbardston for repairs to the Hubbardston public library”Enacted
to the city or town government
FY2025$66,000“the purchase of a replacement boiler at the Hubbardston Center school in the town of Hubbardston”Enacted
to the city or town government
FY2023$50,000“the improvement of public works equipment and facilities in the town of Hubbardston”Enacted
to the city or town government
FY2022$50,000“elevator improvements at the Hubbardston center school in the town of Hubbardston”Enacted
to the city or town government
FY2023$25,000“the Hubbardston senior center in the town of Hubbardston”Enacted
to the city or town government

Enacted earmarks and earmark payments are different things: enacted earmarks are budget clauses, counted three ways above; earmark-account payments are Comptroller payments to the town government and its school districts from accounts classified as earmarks, which can include prior-year and statewide-program money. Either can be larger.

What the state sends and takes back

In FY2027 the state’s cherry sheet sends Hubbardston $756,000 and takes back $12,000 in assessments and charges, a net $743,000.

Sent: estimated receipts

$756,000

FY2027 cherry sheet

Taken back: assessments and charges

$12,000

2% of what is sent

Net

$743,000

receipts less charges

What the state sends
LineFY2027
Unrestricted General Government Aid$585,000
Exemp: VBS and Elderly$33,000
State Owned Land$125,000
Public Libraries$13,000
What the state takes back
LineFY2027
Air Pollution Districts$1,329
RMV Non-Renewal Surcharge$4,240
Regional Transit$6,685

Source: Division of Local Services, FY2027 cherry sheets (C.S. 1-ER receipts and C.S. 1-EC charges), final. Charges include county tax, mosquito control, air pollution districts, planning councils, the MBTA and regional transit, and tuition the town pays for its students who attend charter schools or other districts by school choice. In towns that belong to a regional school district, Chapter 70 goes to the district, not the town, so it does not appear here.

State money to others in Hubbardston

State programs also awarded $143,000 to organizations in Hubbardston other than the town government, FY2016–FY2027.

These are competitive grants to nonprofits, tribal nations, regional bodies, state agencies and businesses located in or serving Hubbardston. They are listed for completeness. They are not counted in the town’s state money or its Fairness Index, because the money does not go to the town government. Where a program has a measure of need for the town, these awards do enter the burden index above; where it has none, they are left out of it. Many of these organizations serve a wider area than the town where they are based.

Awards to named organizations (the town’s share where an award names several towns)
YearRecipientProgramAmount
FY2026Montachusett Regional Planning Commission regional bodyCommunity One Stop for Growth$143,000

Source: the project’s award catalog (state agency award lists and announcements); awards marked as counting toward totals. Earmarks to organizations based in the town are in the earmarks section above, on the second and third measures.

Expected and actual

Hubbardston received $1.4 million in earmarks placed in the city or town and competitive grants over ten years, 63% of the $2.3 million its size, need and institutions predict.

Expected
$2.3M
Received
$1.4M

The expectation comes from a statewide model of all 351 municipalities that uses population, road miles, jobs, poverty, income, tax base, school-aid share and the presence of hospitals, colleges and nonprofits. Those factors explain about 55–60% of the differences between towns. The model leaves out many legitimate reasons a town may receive more or less, such as a single large project, so a gap is a starting point for questions, not a finding about anyone’s conduct.

Earmarks here are placed in the city or town, the second of three measures (enacted); competitive grants are Comptroller payments (paid). Method.

What the town carries

Measured against what it maintains, Hubbardston received 33% of its proportional share of competitive grant awards.

Local road miles

84.1

141st of 351 · 19.2 per 1,000 residents (61st of 351)

Town-owned bridges, replacement cost

$13.5M

scored exposure $3.8M · counts and condition under Roads, bridges and dams

Road-stream crossings

76

179th of 351 · culverts and small crossings

Town-owned hazard dams

0

high or significant hazard

Land area

41.1 sq mi

39% state-owned

Seasonal homes

0%

share of housing units

Peak service population

4,371

residents plus seasonal

Core infrastructure index

0.25

roads, culverts, dams, coast, flood, energy

The burden index divides the competitive awards Hubbardston received from FY2017 to FY2026 by what it would have received if every program had split its money by its own measure of need: road miles for road programs, crossings for culvert grants, town-owned hazard dams for dam repair, jobs for economic development, residents for libraries. 1.0 is proportional. Hubbardston: 0.33. State median: 0.91. Bridges count by replacement cost and condition, not by number, and only bridges the town owns. For the index, bridges are valued from the 2025 inventories at the federal unit cost, and a bridge on a town line is shared among the towns it touches; the Roads, bridges and dams section counts them from MassDOT’s current inventory, so its counts can differ slightly. Ranks run from 1, the most among 351.

State land and growth

State land eligible for PILOT

1,423 acres

5.4% of land area · FY2026

State-owned land PILOT, FY2026

$122,000

payment in lieu of taxes, cherry sheet

PILOT per eligible acre

$86.03

statewide $117 · FY2026

New growth per resident

$11,943

FY2017–2025 · 293rd of 351 · median town $20,524

State land eligible for PILOT is the Division of Local Services’ count of state-owned acres on which the state pays a payment in lieu of taxes; the payment follows the land’s assessed value, not its acreage, so the per-acre figure is a comparison, not the formula. The state-owned share on the land-area tile above is the MassGIS map of all state-owned open space, a wider count. New growth is the assessed value of new construction and improvements added to the tax base, summed FY2017–FY2025 and divided by 2020–24 residents; taxed at the prior year’s rates, it adds to the levy limit beyond 2.5%.

Roads, bridges and dams

Hubbardston has $823,000 of Chapter 90 road money from FY2017–FY2026 not yet reimbursed; it owns one bridge rated poor and no high- or significant-hazard dams.

Chapter 90 apportioned, FY2017–FY2027

$5.8M

$1.3M of it one-time supplements

Reimbursed against it

$4.4M

to 16 October 2026

Not yet reimbursed, FY2017–FY2026 money

$823,000

annual program: 0.4 years of its yearly money · 291st of 351

Town-owned bridges

22

one rated poor; about $1.7M of work on those, by planning estimates

High- or significant-hazard dams

0

the town owns no dams in the state inventory

Bridge, dam and culvert grants, FY2017–FY2026

$418,000

bridges $418,000 · dams $0 · culverts $0

Chapter 90 is the state’s main road program. MassDOT apportions it to every city and town by a formula, and the town is reimbursed after it spends the money on approved work. Counting each payment against the town’s oldest money first, payments to Hubbardston came on average 13 months after the start of the year the money was apportioned for. Statewide, $655 million of FY2017–FY2026 apportionments was not yet reimbursed on 16 October 2026; counting the annual program alone, the median town held about 1.2 years of its yearly money. Money not yet reimbursed is not the same as idle money: MassDOT’s Chapter 90 Advisory Group found 63% of the unspent balance committed to approved projects not yet billed (January 2025).

Chapter 90 by state fiscal year
YearAnnual apportionmentOne-time supplementsReimbursed in the year (any year’s money)Year-end balance, FY2017-on money
FY2017$361,000$0$401,000$119,000
FY2018$356,000$0$343,000$132,000
FY2019$357,000$71,000$431,000$303,000
FY2020$355,000$36,000$492,000$248,000
FY2021$354,000$0$535,000$67,000
FY2022$354,000$280,000$356,000$346,000
FY2023$358,000$0$615,000$89,000
FY2024$358,000$350,000$653,000$143,000
FY2025$357,000$201,000$285,000$416,000
FY2026$635,000$405,000$633,000$823,000
FY2027 (to 16 Oct)$634,000$0$0$1.5M

The full list of the 26 bridges in Hubbardston in MassDOT’s inventory, with each one’s condition, is on the town’s page at massanomics.com/commonwealth.

Every bridge in Hubbardston

Twenty-six bridges in MassDOT’s inventory, three rated poor and one closed, worst first. The list includes bridges the town does not own; costs are shown for town-owned bridges only. Tap the i beside a heading for what it means.

Show Bridges in Hubbardston, MassDOT inventory · 26 rows
Bridges in Hubbardston, MassDOT inventory
BridgeCarriesCrossesTypeOwnerBuiltLowest ratingConditionStatusLast inspectedProposed work
H24018Access Rd (102 ASNACOMET POND)Asnacomet PondCulvertMassDOT1958
rebuilt 2002
3Poor deck 7 · super 7 · sub 3Posted for load2025-07-21
H24002TR Brigham Rd (083 BRIGHAM RD)W BR Ware RiverFootbridgeMassDOT1930
rebuilt 2018
4Poor deck 7 · super 7 · sub 4Open2025-10-01
H24003WilliamsvillBurnshirt RiverBridgeTown19394Poor deck 6 · super 4 · sub 5Closed2025-08-11$1.7M
rehabilitation
H24008Pitchrvll RdTempleton BrookShort spanTown19405Fair culvert 5Open2025-06-23$524,000
likely, at bid prices; $251,000 at unit cost
H24020Route 68 Worcester RdW BR Ware RiverBridgeMassDOT19545Fair deck 5 · super 6 · sub 6Open2026-01-14
H24007Willmvill RdNatty Pond BrookShort spanTown1939
rebuilt 2019
6Fair culvert 6Open2026-01-14$921,000
likely, at bid prices; $442,000 at unit cost
H24011Brigham StBrigham Pond InletBridgeTown19396Fair deck 6 · super 6 · sub 7Open2025-08-11$805,000
work
H24013Raggd HLL RdTempleton BrookShort spanTown19406Fair culvert 6Open2025-07-21$827,000
likely, at bid prices; $397,000 at unit cost
H24022New WstmnstrJoslin BrookBridgeTown20046Fair culvert 6Open2026-10-05$820,000
work
H24004Burnshirt RdBurnshirt RiverBridgeTown1940
rebuilt 2015
7Good deck 7 · super 8 · sub 7Open2025-12-08$2.3M
work
H24009Evergreen RdMason BrookBridgeTown20217Good super 7 · sub 7Open2025-07-07$971,000
unit cost
H24012Hale RdNatty Pond BrookBridgeTown20007Good deck 7 · super 7 · sub 7Open2026-05-04$1.2M
work
H24017Healdvlle RdMason BrookShort spanTown1938
rebuilt 2016
7Good deck 8 · super 8 · sub 7Open2026-08-06$545,000
likely, at bid prices; $261,000 at unit cost
H24021Route 62 Old Bstn TPKW BR Ware RiverBridgeTown20218Good super 8 · sub 8Open2025-11-25$1.4M
unit cost
H24027Route 62 Old Bstn TPKW BR Ware River TribBridgeTown20218Good super 8 · sub 8Open2025-11-25$806,000
unit cost
H24001Other Ped@twn HilW BR Ware RiverFootbridgeMassDOT1850not ratedOpen
H24006Pitchrvll RdHubbardston BrookCulvertTown1960not ratedOpen$52,000
unit cost
H24010Birches RdTempleton BrookCulvertTown1950not ratedOpen$76,000
unit cost
H24015Willmsvil RdConesto BrookCulvertTown1850not ratedOpen
H24016Lombard RdE BR Ware RiverCulvertTown1850not ratedOpen$294,000
unit cost
H24023New TempltnNatty Pond BrookCulvertTown1850not ratedOpen
H24024Route 62 Old Bstn TPKComet Pond OtltCulvertTown1938not ratedOpen$112,000
unit cost
H24025Route 62 Old Bstn TPKComet Pond OtltCulvertTown1938not ratedOpen$251,000
unit cost
H24026Route 62 Old Bstn TPKComet Pond OtltCulvertTown2009not ratedOpen$91,000
unit cost
H24028Lombard RdE BR Ware RiverCulvertTown1960not ratedOpen$184,000
unit cost
H24029Raggd HLL RdTempleton Brook TribCulvertTown1940not ratedOpen$78,000
unit cost

Chapter 90: MassDOT apportionments and the Comptroller’s payment records (CTHRU), FY2017–FY2027; “not yet reimbursed” means apportioned money not found in the payment records. Bridges: MassDOT’s bridge inventory and the federal National Bridge Inventory, town-owned structures only; a bridge on a town line counts in part to each town. Dams: Office of Dam Safety inventory, town-owned only. Repair grants: EEA, Division of Ecological Restoration and MassDOT award lists. These amounts are not in the town’s state money totals above. Method.

Costs and the 2½% limit

State aid covered 6.3% of Hubbardston’s general-fund spending in FY2025, down from 8.0% in FY2006.

State aid as a share of general-fund spending

FY2006

8.0%

$488,000 of $6.1M · median town 14.1%

FY2016

6.5%

$523,000 of $8M · median town 12.2%

FY2025

6.3%

$712,000 of $11.4M · median town 11.5%

Net of state charges, FY2025

6.2%

FY2010: 7.4% · median town 10.0%

State aid is the gross cherry sheet as entered on the tax rate recap; spending is the town’s general-fund expenditures as filed with the Division of Local Services. Net subtracts the charges the state assesses on the same cherry sheet (charter and school-choice tuition, transit, county and other assessments), itemized from FY2010.

Hubbardston’s own cherry sheet carries no Chapter 70 for pupils in its regional district; the state paid $4.8 million in FY2025 Chapter 70 to the district on its behalf, outside these figures, while the town’s assessment to the district sits in its spending. For a regional member the share understates state support for school costs.

Hubbardston’s state aid did not keep pace with either price measure: FY2025 aid was 5.9% below its FY2006 aid grown by Boston-area consumer prices and 16.4% below grown by the government price index.
FY2006 aid
$488,000
At FY2025 consumer prices
$757,000
At FY2025 government prices
$852,000
FY2025 aid
$712,000

Gross state aid went from $488,000 in FY2006 to $712,000 in FY2025, +45.9% in dollars. Consumer prices are the Boston-area CPI-U, up 55.1% over those years; government prices are the federal price index for state and local government purchases, up 74.5%. Fiscal-year averages.

Fixed costs against the 2½% limit, FY2016–FY2025

Health insurance, FY2016–25

+0.7%

$156,000 to $158,000 · all towns +54.0%

All fixed costs, FY2016–25

+71.8%

$470,000 to $808,000 · all towns +53.0%

Years squeezed

5 of 9

fixed costs grew faster than allowed levy growth

Health insurance

3 of 9

years it grew faster than allowed levy growth

Nine years at 2.5% add 24.9%. Grown that way from FY2016, Hubbardston’s health insurance would have been $195,000 in FY2025; it was $158,000, $38,000 below the path. Its fixed costs would have been $587,000 in FY2025; it was $808,000, $221,000 above the path.

Fixed costs are employee benefits, retirement, insurance and similar costs in the general fund; health insurance comes from a separate DLS report. Allowed levy growth is 2.5% plus new growth, as a share of the prior year’s levy limit; a year counts as squeezed when fixed costs grew by a larger percentage.

Flag: health insurance changed by more than 30% in one year in FY2023 (+40%). Swings this size usually mark costs moving between budget lines, into or out of trust funds, or into the state’s Group Insurance Commission, so the comparison may reflect accounting as well as cost.

Local earmarks against the health-insurance increase

Over the nine budgets, earmarks to Hubbardston’s government came to $291,000, 265.3 times the $1,097 rise in its health insurance.

Local earmarks FY2017–FY2025 (enacted, nine budgets) against the FY2016–FY2025 rise in health insurance
MeasureEarmarksShare of the increaseAll towns, pooled
To the city or town government$291,000265.3 times13.0%
Placed in the city or town$291,000265.3 times41.2%
Everything placed$291,000265.3 times45.2%

An earmark is a one-year appropriation; a health-insurance increase recurs in every later budget. Earmarks are counted on the three measures and are not adjusted for the January 2024 mid-year cuts or the FY2026 hold. All towns: pooled over the towns that reported health insurance in both years. All dollars nominal. Method.

The Commonwealth in Hubbardston

Hubbardston has 10,522 acres of mapped state conservation and recreation land and 1,802 acres of land coded as chapter land.

State conservation and recreation land

10,522 acres

40.0% of Hubbardston’s land

Chapter 61, 61A and 61B land

1,802 acres

6.9% of Hubbardston’s land · 75 parcels

Agricultural Preservation Restrictions

46 acres

state farmland program

Conservation restrictions

259 acres

all holders; each approved by the state

What the map shows
LayerParcelsAcres
State conservation and recreation land20410,522
Other state-owned parcels (assessor records)16510,602
Chapter 61 forest land21893
Chapter 61A farm land39630
Chapter 61B recreation land15279
Partly enrolled (mixed-use parcel)512,237
Agricultural Preservation Restriction246
Conservation restriction10259
Watershed preservation restriction8706
State-owned parcels by agency (assessors’ records)
AgencyParcelsAcres
DCR Water Supply Protection1369,064
Fisheries and Wildlife291,539
Named state conservation and recreation land
PlaceAgencyAcresArticle 97
Ware River WatershedDCR Water Supply Protection8,577
Hubbardston State ForestDCR State Parks and Recreation1,183
Hubbardston WMADCR Water Supply Protection391
Phillipston WMAFish and Game (MassWildlife)166
Natty Brook AccessFish and Game (MassWildlife)93
Wachusett Mountain State ReservationDCR State Parks and Recreation92
Ware River Rail TrailDCR State Parks and Recreation13
Moosehorn Pond AccessFish and Game (MassWildlife)7
Williamsville Pond Boat RampDCR Water Supply Protection0

State conservation and recreation land: MassGIS Protected and Recreational OpenSpace, land owned by a state agency, with MassGIS’s acres. State-owned parcels: assessors’ records (MassGIS standardized parcels, Commonwealth reimbursable land, codes 910–919), mapped acres; this is the land the state pays PILOT on, so it overlaps the open-space layer, and the Division of Local Services’ own acreage, above, is the official count. Chapter land: parcels coded 6, 7 and 8 (Chapter 61 forest, 61A farm, 61B recreation), taxed at their current use rather than full market value; towns code chapter land differently, and mixed-use parcels with a chapter portion are shown but not counted in the acres. Restrictions: MassGIS open space; restricted private land shows its holder, not its owner. Acres are mapped acres and may differ from deeds. In Hubbardston the assessors’ records show 10,602 acres of state-owned parcels against 1,423 acres in the Division of Local Services’ count, which is the basis of the cherry-sheet PILOT; land such as reservoir watershed is counted differently.

Roads: who maintains what

Of 86.5 miles of public road in Hubbardston, the state maintains 0.0 (0%); local government and others maintain the rest.

JurisdictionMilesShare
MassDOT0.00%
Town-accepted84.197%
Unaccepted public ways2.02%

Habitat, forest and water

Hubbardston has 6,044 acres of mapped core habitat, 23% of its land area; 1,655 of those acres are outside any protected land.

Land and Water Index

74 / 10062nd of 351 (1 = most forest kept, most core protected, least impaired water)

Forest to 1999
67
Forest since 2001
50
Gap
88
Water
91

Rank under other weightings: 43rd to 87th.

Stable high: above 55 under every weighting

Hubbardston kept about as much of its 1971 forest as the typical town; has kept about as much of its forest since 2001 as the typical town; has more of its core habitat on protected land than most; and less of its assessed water is on the impaired list than in most towns; its score of 74 stays between 43rd and 87th under every weighting tested.

Core habitat (BioMap)

6,044 acres

23% of its land area · 193rd of 351 · median town 25%

Core habitat on protected land

4,389 acres

73% of its core · state, federal, town, land-trust, restricted or chapter land

Forest, 1971 to 1999

-6.1%

22,898 → 21,511 acres · median town -9.7% · 114th of 351 (1 = most gained)

Assessed water impaired

19%

193 of 584 lake acres; 1.0 of 18.7 river miles · median town 67% · 32nd of 351 (1 = least)

Map of the habitat, wetland and protected layers, the forest record back to 1830, and the lakes and rivers on the impaired list: Hubbardston: habitat, forest and water. All 351 on one map: habitat, forest and water, statewide.

Core habitat is BioMap (2022), the land the state’s biologists mapped as most important for rare species, intact forest, wetlands and streams. Protected land is state, federal, municipal and land-trust open space with permanent protection, land under a conservation or farmland restriction, and chapter land (the weakest of the three; it can leave the program on notice). Forest is MassGIS land use, 1971 to 1999, one method, with forested wetland counted as forest; later maps use different methods and are shown on the land page. Forest since 2001 is USGS Annual NLCD land cover, 2001 and 2023 (Collection 1). Impaired water is MassDEP’s 2022 Integrated List, assessed waters only; category 4C listings are for causes that are not pollutants, such as invasive plants. Shares are of the municipality’s land area (Census 2020).

Schools

Hubbardston’s required school contribution is 2.3% of median household income, 275th highest of 351.

Chapter 70 aid, FY2026

$4.9M

attributed to the town

Required local contribution

$4.8M

FY2026

Share of household income

2.3%

275th of 351 (1 = highest)

Real aid per pupil, FY2017–26

−6%

after inflation

Hubbardston has no school district of its own. Its pupils attend Quabbin and Montachusett; Hubbardston accounts for 29% and 2% of their foundation budgets, in that order. Aid and contribution are DESE’s attribution to the town. How a region splits its assessment among members is set by its own agreement and is not published statewide.

Real figures use the CPI-U, fiscal-year average, in FY2026 dollars. The required contribution is the local share the state sets under the Chapter 70 formula; the share of income divides it per household by the town’s median household income.

School buildings

The Massachusetts School Building Authority approved grants of up to $481,000 for schools serving Hubbardston, FY2017 to August 2026.

Approved, Hubbardston’s share

$481,000

$110 per resident (238th of 351)

Projects

1

approved, July 2016 to August 2026

Statewide

$8.85B

shared by 280 of 351 municipalities

The Massachusetts School Building Authority is an independent state authority funded by one penny of the 6.25% state sales tax. Its Board approves grants for new and renovated schools (the Core program) and for roofs, windows and boilers (Accelerated Repair), and pays a share of eligible costs that rises with a community’s need. These grants are shown on their own: they are not in Hubbardston’s state money, its Fairness Index, its burden index or its peer comparisons. The Comptroller’s payment records do not carry the authority’s payments, and a single building can outweigh a decade of other state aid.

School building grants approved, newest first
YearSchoolDistrictProgramMaximum grantHubbardston’s share
FY2020Hubbardston Center SchoolQuabbinAccelerated Repair (Roof)$1.6M$481,000 (29%)

Grants to a regional district are shared among its member towns by each town’s share of the district’s enrollment (DESE, FY2026), shown in parentheses.

Cost after approval. Of the one project closed with a final audit, Hubbardston’s share of the final cost was $739,000 against its share of the approved budget of $867,000 (under by $127,000); the local share moved from $385,000 to $302,000. Approved budgets include contingency.

Amounts are the Maximum Total Facilities Grant the Board approved, a ceiling that includes contingency; the authority pays eligible costs as they are incurred and settles the final grant at audit. Year is the state fiscal year of the Board vote. Method.

Peers

Hubbardston ranks 6th of 11 on earmark dollars placed in the city or town per resident among itself and its ten nearest peers.

Peers are the ten municipalities nearest to Hubbardston on population, income need and tax-base need. The best and lowest performers are the highest and lowest on earmark dollars placed in the city or town per resident in the wider class of 30 nearest, the second of three measures.

MunicipalityFairness IndexFormula aid per residentCompetitive per residentEarmarks placed in the city or town, per resident (enacted)Burden indexSchool contribution, share of income
Hubbardstonthis town59$16,583$264$66.580.332.3%
Avonpeer46$10,665$1,049$1013.023.0%
Ashbypeer56$15,057$337$62.290.632.3%
Southamptonpeer49$11,984$317$22.651.742.9%
West Bridgewaterpeer41$10,584$177$65.300.302.9%
Hopedalepeer54$14,756$309$141†0.383.2%
Millvillepeer56$14,661$545$1141.932.0%
Westminsterpeer · best in class of 3048$12,585$85.79$1,114†0.302.9%
Georgetownpeer46$10,873$155$26.520.602.7%
Rochesterpeer43$11,142$331$47.110.453.3%
Suttonpeer44$10,223$840$1071.913.1%
Westminsterbest in class of 3048$12,585$85.79$1,114†0.302.9%
Shutesburylowest in class of 3062$14,882$4,462$00.502.0%

Formula aid per resident is the ten-year gross total; competitive grants are ten-year totals paid, FY2017–FY2026; earmarks are enacted clauses placed in the city or town over the same ten state budgets. † More than half of that municipality’s placed earmarks went to organizations rather than to its government. Add up to ten towns to the table; adding needs JavaScript.

Sources

Every figure traces to a public record.

Every figure on this page is built from these public sources. Method and limits.

Parcenomics helps towns turn numbers like these into a plan. Municipal services · Contact

Massanomics Weekly Every Tuesday

Your city or town, in the numbers that matter.

  • This week’s story, with where your city or town stands
  • Economics, housing and the state money that reaches you
  • Land, climate, history and politics
  • Side-by-side findings that show how it all connects
Free
every week
Sign up
One email a week. Unsubscribe from any issue.

Feedback. Every figure here is built from public records, and every claim in the report is checked against its source before it is published. The work has also been reviewed independently. If you believe something should be corrected or clarified, let us know. We will look into it promptly, and any correction is published with its date on the Method page. Provide feedback · Contact us